KUALA LUMPUR, Oct 6 (Bernama) -- AM Intelligence (AMI), the artificial intelligence (AI) infrastructure platform set up by the promoters of Greenko, has announced two further firm and binding orders for 20,000 NVIDIA Rubin graphics processing units (GPUs) to be deployed as NVIDIA Vera Rubin NVL72 rack-scale systems.
Building on its first AI factory in Hyderabad, India, the expansion is designed to give cloud providers, enterprises and AI developers access to large-scale computing capacity closer to where they build and deploy AI.
These orders are in addition to AMI's inaugural commitment announced on Aug 25 for 9,000 NVIDIA Rubin GPUs at its first AI factory in Hyderabad. The follow-on capacity, totalling approximately 70 megawatts (MW), will be deployed in Malaysia and India, with delivery scheduled for the second quarter of 2027.
“Both facilities will be built to the same architecture standard as the Hyderabad AI Factory, integrating the NVIDIA Vera Rubin platform with high-throughput RDMA over Converged Ethernet (RoCE) networking for fast, efficient data movement, alongside advanced storage systems.
“Each site is engineered for high rack power density and liquid cooled throughout, allowing the infrastructure to accommodate successive generations of AI silicon within the same physical footprint,” said AMI Chairman, Anil Chalamalasetty in a statement.
Taken together, the three orders bring AMI's committed frontier compute to approximately 29,000 Rubin GPUs and close to 100 MW of capacity.
AMI said it plans to bring an additional 300 MW of capacity to market over the next 15 months, involving capital expenditure of more than US$20 billion. (US$1 = RM4.08)
The company has developed a pipeline of approximately 400 MW of Compute-as-a-Service capacity across global locations, including India, the United States, Europe and Malaysia. The three orders placed to date represent the first committed tranche within that pipeline, while the balance is under development for delivery in subsequent phases in 2027 and early 2028.
The pipeline advances AMI's stated intention to bring one gigawatt (GW) of Compute-as-a-Service capacity to global AI workloads, within a broader programme of five GW of powered AI data centres.